Activity | Duration (days) | Predecessor | |
A | Create the EHR vision | 5 | – |
B | Identify the planning horizon | 10 | A |
C | Obtain buy-in from affected parties | 30 | B |
D | Develop a financing and acquisition strategy | 10 | C |
E | Develop functional, data, and technical strategies | 45 | C |
F | Conduct vendor selection | 45 | D, E |
G | Plan the EHR implementation | 15 | C, E, F |
H | Conduct benefits realization study | 10 | A-H |
- Draw the PERT or GANTT chart for this implementation based on the information provided.
- Indicate the critical path on the PERT or GANTT chart.
- Your file should be in Microsoft Word, Microsoft PowerPoint, Microsoft Excel, or Adobe Acrobat format.
- Cite all sources in APA format.
- Submit your PERT or GANTT chart for grading.
- Reminder: You must upload your completed document using Browse My Computer. Then, hit the Submit button to successfully complete the assignment submission process. Do not copy and paste text into the text box.
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code “Newclient” for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.
The post gantt chart 7 appeared first on The Nursing Hub.